Street Acceptance Submittal
|
|
|
Requirements for
Record Drawing Inspection
A project is eligible for
record drawing inspection at such time as the
pavement and drainage facilities have been completed
and the subdivision plat and required right-of-way
of easement instruments have been recorded in the
Official Public Records of Harris County.
To schedule a record drawing inspection, the
Engineer of Record shall submit the following:
- A copy of the approved drawings for the project.
These drawings shall be stamped record drawings,
sealed by a licensed engineer and shall have the
following statement. "The project is
constructed in general conformance with these plans
and elevations on these drawings represent what was
constructed within engineering tolerances."
- Two copies of the recorded plat.
The Engineer of Record shall upload the
following:
- A completed "Request for Initial Inspection
Form" as promulgated by the County Engineer.
- A completed "Statement of Substantial
Compliance Construction Materials Testing
Project Review" as promulgated by the County
Engineer demonstrating the project met all
testing and performance requirements.
- A copy of the development permit or paving &
organized storm sewer permits.
- A copy of the financial surety worksheet and
receipt.
- Complete the plat account information on our
website for the developer & contractors with
email addresses.
- Complete the paving & drainage section on
our website.
Requirements for Record Drawing Inspection
Testing Laboratory
Surety/Bond Cancellation Inspection Form
|
|
|
|
Additional Forms
|
|
|
|
|
|
Contact Us
|
|
| |
Acceptance
Manager: David Weaver
|
| |
10555 Northwest Freeway
Suite 144
Houston, Texas 77092
|
|
|
|
|
|
|
|
|
|